Worked example — default entered values
Load 1 starts at 2.5×; entered margin 20%. Manufacturer transient confirmation required.
Load 1: 1.6 kW ÷ PF 0.9 = 1.778 kVA · selected start 2.5× · Load 2: 0.8 kW ÷ PF 0.8 = 1.000 kVA · Entered margin: 20% · Entered environment/location scenario: Outdoors in an open, manufacturer-permitted location
One explicitly selected load starts while every other entered load is already running.
Each startup multiplier is entered by the user; it is not a universal motor value.
Startup power factor is approximated by the entered running power factor.
Waveform, voltage/frequency dip, phase, earthing, nonlinear loads and altitude/temperature derating are not modelled.
Confirm nameplate input, phase, voltage, frequency, waveform, earthing, transient kVA, voltage dip, load-step limits and derating. Sensitive, nonlinear, welding, lifting or critical loads require specialist assessment.
PLANNING ESTIMATE. Nameplates, waveform, phase, voltage, frequency, earthing and manufacturer transient/load-step limits govern. Never convert the result directly into a generator product size.
Source register · registry version 1.0.0
Cummins, How to size a genset: Proper generator set sizing requires analysis of parameters and loads — effective 2007-07-01 — accessed 2026-07-24
Cummins, T-030: Liquid-Cooled Generator Set Application Manual — effective 2015-02-01 — accessed 2026-07-24
Health and Safety Executive, Construction hazardous substances: Carbon monoxide — accessed 2026-07-24
Formula researched 2026-07-24